Not always. Changing a window specification does not need a consent amendment where an equivalent-performing product is substituted and the change is treated as a minor variation, recorded on the consent file. That's why UNO Windows & Doors supports architects, builders and developers through window and door specification changes, providing product information, performance data, project-specific R-values and standard details in UNO Hub. The Building Consent Authority makes the final decision.
Changing a specification can be straightforward where equivalent-performing alternatives are proposed. In many cases, this may be treated as a minor variation, subject to council review and recording. However, the Building Consent Authority ultimately determines the appropriate pathway based on the supporting performance evidence and the effect of the change on Building Code compliance.
The Building (Minor Variations) Amendment Regulations 2024 clarify that substituting a comparable product can be treated as a minor variation, meaning councils are not required to issue an amended building consent, provided performance equivalence and compliance with the Building Code are maintained. In these cases, councils record the variation on the consent file without requiring a full redraw of plans, making specification changes less disruptive and easier to manage.
UNO Windows & Doors supports architects, builders and developers through window and door specification changes on New Zealand multi-residential and commercial projects. UNO reviews the existing specification and provides the product information, performance data, project-specific R-values and standard details needed to support a proposed change, all in one place through UNO Hub.
Last reviewed: November 2026
Councils assess changes based on whether the approved design intent and Building Code compliance pathway are altered, not simply whether a different product is named.
A window and door change is generally treated as a product substitution when:
In these circumstances, the design remains the same. The building is being constructed in the same way, using a different brand but comparable product to achieve the same outcome.
What is more likely to be treated as a design change requiring a formal amendment, where it:
The key distinction is simple:
If the change alters how Building Code compliance is achieved, it is a design change.
If it only changes which compliant product is used within the same approved design, it is a product substitution.
Councils make the final determination, but MBIE guidance recognises product substitution as a low-risk change when the compliance pathway and design intent are unchanged and the change is supported by clear documentation.
If you are still unsure you can use Simpli's minor variation tool here, the guides below, or discuss with your local BCA.
MBIE Product Substitution Guidance
Yes. MBIE’s Product Substitution Guidance states that if you intend to substitute a building product originally specified in your building consent, you must notify the Building Consent Authority and show how the new product will continue to comply with the Building Code.
Not always. If the change meets the product substitution or minor variation criteria, councils can approve it without issuing an amended building consent. However, councils must be notified and will confirm the correct pathway.
Usually no. For minor variations, councils generally accept updated window and door schedules, updated specifications, and references to standard manufacturer details. Full redraws are typically only required where sizes, structure, or weathertightness details materially change.
In this situation, councils generally treat the change as a product substitution only.
Where:
The change can usually be addressed through updated schedules and references, rather than new drawings. Councils focus on confirming that the original weathertightness design intent has not changed. If you are unsure, check with your local BCA for guidance.
A formal amendment is more likely to be required if the change:
If the flashing approach changes how moisture is managed, councils will typically require further assessment and may request updated drawings or an amendment.
UNO Hub supports changing window specifications by giving you everything you need in one place:
By bringing specification support, technical information and project-specific R-values together in one place, UNO Hub helps teams assess proposed window and door changes sooner and keep the approval process moving.
The first step is to gather the information needed to support a potential specification change before engaging with council.
UNO can:
You can also use the Guides section in UNO Hub to access UNO’s MasterSpec information directly, making it easier to progress your window and door specification from one place.
Visit UNO Hub:
www.unowindows.co.nz/hub
UNO does not determine whether a change is a product substitution or a minor variation. That decision sits with the Building Consent Authority (council).
Once the information is prepared, the proposed change should be submitted to council by the consent holder or their agent, who will confirm whether it can be approved as a minor variation or requires a formal amendment.
Disclaimer
The information in this article is provided for general information purposes only and reflects the Building Code documents and standards current at the "Last reviewed" date shown on this article. It does not constitute technical, engineering or legal guidance for any specific project. Building Code documents and standards are subject to change; readers should refer to the current version of the relevant document and confirm all requirements with their designer, engineer and Building Consent Authority before proceeding. Construction R-values and product performance are project-specific and should be confirmed using the values generated in UNO Hub for the project concerned. UNO Windows & Doors accepts no liability for any loss or outcome arising from reliance on, or interpretation of, the information provided.